Create an SCM project configuration - Create an SCM project configuration - Brainware - Solution Configuration Manager - Brainware/Solution-Configuration-Manager/23.1/Solution-Configuration-Manager-User-Guide/Manage-Projects/Manage-Project-Configurations/Create-an-SCM-project-configuration - 23.1 - 23.1

Solution Configuration Manager User Guide

Platform
Brainware
Product
Solution Configuration Manager
Release
23.1
License
ft:lastPublication
2023-11-09T20:39:19.709000
ft:locale
en-US
To create an SCM project configuration, complete the following steps.
  1. In the navigation bar, click Manage Projects.
  2. In the Manage Project Configuration page, in the empty project row, complete the following substeps.
    1. Type a project name in the Project Name field.
    2. From the Package list, select a package.
    3. From the Version list, select the version number.
    4. From the Connection Group list, select a connection number.
    5. Optional. SCM Projects are active by default. To deactivate the project, clear the check box in the Active column.
  3. Click the Insert link.