You can use output mapping together with the sys_task_assignee system variable to capture the user assigned to a completed task. This allows you to store the assignee information in a process variable and reuse it later in the process, for example for notifications, reporting, or routing decisions.

Note: The sys_task_assignee variable is a system variable and cannot be edited.

You can use this approach when the assignee must be reused later in the process (for example in notifications or approvals). If output mapping is not configured, the assignee value is not stored and cannot be used later.

To create a process that captures the assignee of a completed task:

  1. Create a form.
  2. Create a process that includes a user task.
  3. From the Properties pane, select the form you created from the Form name drop-down list.
  4. From the Mapping type drop-down list select Map variables.
  5. Deselect the User task by clicking anywhere in the white space and then click Edit Process Variables from the right pane.
  6. Click the + icon and enter a name for the process variable in the Name field.
  7. From the Type drop-down list select Primitives then select string and then click Update.
  8. Select your User task again and from the sys_task_assignee drop-down menu under Output mapping select the process variable you have just created.
After the task is completed, the process variable contains the assigned user. The assignee is captured after the task is completed and becomes available to all following steps.