The last major step for validating that your platform is working properly is to create tasks.

To manually create tasks:

  1. In Hyland RPA Web Manager, in the left pane, select Tasks.
  2. In the Tasks pane, click Add.jpg.
  3. In the Create task dialog box, select your Process from the drop-down list.
  4. Select PRO from the Task type drop-down list.
  5. In the Amount field, enter 5.
  6. Select Pending from the Status drop-down list.
  7. Select Now from the Priority drop-down list.
    Note: Source, Input data, Diversity, Execution date, Check diversity, Redoable, and Create another task are optional, and not needed for validation.
    The Tasks pane shows the 5 pending tasks.

If RPA Conductor is running on your available agent within the group assigned to the process, work on these tasks will begin immediately because the Priority is set to Now.

In the background, the RPA Conductor saw that there were tasks to do, downloaded the process file and the required version of the Activities to the instance where the agent resides, and started processing.

In the Tasks pane, click to see that the status has updated to Finished after the 5 tasks have been successfully completed.

If it does not start within a few minutes, restart the Hyland RPA Conductor service in Windows Services.